On June 28, “OKB Spetstyazhproekt” and “OOO NLK” (both members of the “Spetstyazhavtotrans” Group of Companies) completed the delivery of the first batch of oversized heavyweight equipment in 2019 to the berth of the Amur GPP.

The first and largest cargo is a demethanizer column. It is designed for natural gas cleaning and producing pure methane. The length of the column is 88 meters, the diameter is 7.46 meters, and the weight is 835 tons.

The second largest cargo is the diazotization column.  Its dimensions: length – 59 meters, diameter – 8.5 meters, weight – 867 tons.

16 pieces of equipment with a total weight of 3,000 tons arrived on 4 barges.

The next crane vessel with equipment will arrive at the seaport of De-Kastri at the end of July.  Specialists of the “Spetstyazhavtotrans” Group of Companies will deliver 34 more cargoes to the Amur GPP, including oversized and heavyweight cargoes.