Multimodal transportation of 10 equipment units from Saint Petersburg to the Sayano-Shushenskaya Dam.

Heavy hydro turbine assemblies were shipped by a river-sea vessel “Arsenal” through the Northern Sea Route.

Due to the professional approach and logistic scheme optimization the delivery of water wheels, rotor frames and oil tanks was completed within two years instead of the scheduled tree.