On July 4, specialists of OKB Spetstyazhproekt delivered the full volume of cargo from the MV Regine crane ship to the berth of Amur GPP.

The route length: 2.5 thousand kilometers (237 km along the Tatar Strait from the port of De Kastri to Nikolaevsk-on-Amur, 1923 km along the Amur River and 212 km along the Zeya River to the berth of the Amur Gas Processing Plant).  The route was covered in a period of 18-20 days.

OKB Spetstyazhproekt delivered 29 units of licensed equipment with a total weight of 4,593.17 tons.

The next delivery to the berth of Amur GPP is expected in mid-August 2020.

In total, in the 2020 season, the volume of deliveries of the equipment to the Amur GPP totals to 43 units of equipment with a total weight of about 8 thousand tons. Spetstyazhavtotrans will deliver more than 4.5 thousand tons of licensed cargo. The involved fleet was specially built to transport oversized heavyweight equipment to the Amur GPP.