On November 10, the specialists of «OKB Spetstyazhproekt» LLC have delivered to the pier of the «Volgogradneftemash» plant the last 5th cargo for PJSC «Tatneft» under the contract with «Navinia Rus» LLC. In scope of delivered equipment is a fractionating column weighing 237 tons (48.5 x 7.4 x 6.2 m) and 4 coking chambers weighing 254 tons (32.6 x 8.8 x 8.6 m).

The project for the delivery of 5 cargoes from workshop No. 6 of the OJSC «Volgogradneftemash» plant to the pier of the plant was carried out from October 19 to November 10.
The just made equipment was taken out of the workshop. The transportation route, although small, passes along the railway tracks, and the transport window for crossing the railway line along the technological crossing is short and is at night.
The head of the transport project Andrey Ovdienko comments: “We know the work well. Everything was completed on time and without any remarks”.