Specialists of OKB Spetstyazhproekt installed a drying drum weighing 550 tons on the territory of the Kronospan DSP plant in the Kaluga Region. The load was lifted to a height of 9 meters and placed on roller bearings.

The installation process took 4 days and was carried out using the SBL-1100 system.